Variation and Delay Cost Recovery

Urban Renewal Civil Infrastructure, Melbourne

Client: Civil contractor
Location: Melbourne, Victoria
Services: Claims Preparation, Post-Contract Support

The Problem

A civil contractor delivering an urban renewal infrastructure package faced a growing volume of unresolved variations. Latent ground conditions, contaminated soil disposal, dewatering, design changes and authority delays had affected the works across two separable portions, and the associated time and cost had not been recognised.

Our Role

PCAG provided claims preparation and commercial support throughout delivery, working with the contractor’s project and commercial team to establish entitlement, quantify the impact and present each claim in a form the Superintendent could assess.

Deliverables

  • A structured programme of variation claims, each with formal claim correspondence and valuation schedules
  • An extension of time delay-cost submission covering both separable portions, supported by a detailed valuation workbook
  • Formal claims for inclement weather and authority-related delays
  • A response to a principal backcharge claim
  • Management briefings on the rebaselined cost position

Outcome

The contractor reached a negotiated settlement with the principal covering the variations package and the delay-cost claim, with the settled items closed out through Superintendent certification.